Basement
- HVAC - Has been inspected. Grills will be installed after painting.
- Water Heater - The existing water heater is in good condition. We recommend seeing if there is any issue with it before spending the money on a different one. Easy enough to do at anytime.
- Carpet - Extra. will be removed next week. Julia and LL to spec new asap.
- Cabinet Hardware - Julia and LL to spec new asap.
- Sound system install - Wired by electrician finish after painting.
- Pipe Heating - Is done.
- Repair pantry shelf - to be done at finish
- New washer and Dryer - Extra. Ordered and waiting for delivery.
- Install pet door under stairs - Extra. Will be done at finish.
First Floor
- Front light - to be done before painting
- Restore and weather proof front door; brass kickplate - Extra. Brass kick plates have been ordered. Door will be restored when the weather is warm enough to remove it.
- Stained glass over front door - Extra. Looking for salvaged pieces that will work.
- Speaker installation - Kitchen speakers will be installed after painting
- Pantry sink/toilet - LL to spec new.
- Keystone for fireplace in Dining Room - Looking
- New Plaster moldings - Extra. 4/12. After sheet rock and before plaster. within next 2 weeks.
- Replace windows - Extra. All windows to be replaced when they are delivered. By 5/1.
- Plaster Finish Work - Scheduled for 4/11
- Appliances - Have been ordered and are ready for installation.
- Plumbing fixtures - Mostly ordered. LL to finish up.
- Paint - Starts 4/26
- Finish Floors - After painting. Probably 5/15.
- Install sconces - At finish after painting
- Range hood - Range hood will go in during phase II and run straight up through soffit through roof
Second Floor
- Guest bath vanity design - After rock and plaster.
- Tile/counter materials ordered - After cabinet installation. Approx. 5/7
- Glass for shower - When tile is finished.
- Steam unit for MBath - Steam bath cannot go under bench it needs too much clearance. I want it to go in a soffit over the toilet in the master bath water closet.
- Medicine cabinet - for guest bath has been framed in same location as original.
- Sconces - For Guest Bath to be supplied by Owner.
- TV for MBed - Size, brand and model to be determined by Client. Installed at finish.
- Design Master Bath - Ready to look at.
- Closet designs (2) - 4/11
- Closet Installation - 5/7
- Plaster/finish work - 4/11
- Window replacement - 5/1ish
- Sound system (Mbed/bath) - Wired by electrician finish after painting.
- Replace hall recessed light fixtures to white - Extra.
- T-stat - Wifi brand TBD. installed at finish
- Paint - Starts 4/26
Third Floor
- Girls Bath vanity shops - by 4/10
- Shelf/cabinet over toilet - TBD
- Finalize finishes for bathroom (tile/paint) - LL & Julia
- Eliza’s desk design - ASAP. Eliza to submit updated plan for redlining.
- Amelia’s closet design - 4/1
- Windows (4)- 5/1ish
- Paint - Starts 4/6
Exterior
- Repoint Brick - Sometime in May