Friday, April 5, 2013

Schedule



Basement
  • HVAC - Has been inspected.  Grills will be installed after painting.
  • Water Heater -  The existing water heater is in good condition.  We recommend seeing if there is any issue with it before spending the money on a different one.  Easy enough to do at anytime.
  • Carpet - Extra. will be removed next week.  Julia and LL to spec new asap.
  • Cabinet Hardware -  Julia and LL to spec new asap. 
  • Sound system install - Wired by electrician finish after painting.
  • Pipe Heating - Is done.
  • Repair pantry shelf - to be done at finish
  • New washer and Dryer - Extra. Ordered and waiting for delivery.
  • Install pet door under stairs - Extra.  Will be done at finish.
First Floor
  • Front light - to be done before painting
  • Restore and weather proof front door; brass kickplate - Extra.  Brass kick plates have been ordered. Door will be restored when the weather is warm enough to remove it. 
  • Stained glass over front door - Extra.  Looking for salvaged pieces that will work.
  • Speaker installation - Kitchen speakers will be installed after painting
  • Pantry sink/toilet - LL to spec new.
  • Keystone for fireplace in Dining Room - Looking
  • New Plaster moldings - Extra. 4/12. After sheet rock and before plaster. within next 2 weeks.
  • Replace windows - Extra. All windows to be replaced when they are delivered. By 5/1.
  • Plaster Finish Work - Scheduled for 4/11
  • Appliances - Have been ordered and are ready for installation.
  • Plumbing fixtures - Mostly ordered. LL to finish up.
  • Paint - Starts 4/26
  • Finish Floors - After painting. Probably 5/15.
  • Install sconces - At finish after painting
  • Range hood - Range hood will go in during phase II and run straight up through soffit through roof
Second Floor
  • Guest bath vanity design - After rock and plaster.
  • Tile/counter materials ordered - After cabinet installation. Approx. 5/7
  • Glass for shower - When tile is finished.
  • Steam unit for MBath - Steam bath cannot go under bench it needs too much clearance. I want it to go in a soffit over the toilet in the master bath water closet.
  • Medicine cabinet - for guest bath has been framed in same location as original.
  • Sconces - For Guest Bath to be supplied by Owner.
  • TV for MBed - Size, brand and model to be determined by Client. Installed at finish.
  • Design Master Bath - Ready to look at.
  • Closet designs (2) - 4/11
  • Closet Installation - 5/7
  • Plaster/finish work - 4/11
  • Window replacement - 5/1ish
  • Sound system (Mbed/bath) - Wired by electrician finish after painting.
  • Replace hall recessed light fixtures to white - Extra. 
  • T-stat - Wifi brand TBD. installed at finish
  • Paint - Starts 4/26
Third Floor
  • Girls Bath vanity shops - by 4/10
  • Shelf/cabinet over toilet - TBD
  • Finalize finishes for bathroom (tile/paint) - LL & Julia
  • Eliza’s desk design - ASAP. Eliza to submit updated plan for redlining.
  • Amelia’s closet design - 4/1
  • Windows (4)
    - 5/1ish
  • Paint - Starts 4/6

Exterior
  • Repoint Brick - Sometime in May