Project Overview
Project start date 1/2/13
- New kitchen
- New 36" Range - downdraft
- New 36" fridge - Sub-Zero
- New DW
- New Coffee maker
- New cabinetry
- Raise windows
- Relocate doors to porch - to dining room (?)
- Screen porch
- Screen in deck off kitchen
- Railings
- Roof deck above
- Storage below - bikes etc.
- Renovate 2nd floor bath.
- 3rd floor bath
- Re-tile
- Paint
- Build new master suite - 2nd floor
- New door to deck
- Build master bath/closet over kitchen
- New door to Master bath
- New windows at front of house.
- Update or replace HVAC
- Split into (2) zones - basement & 1st floor, 2nd & 3rd floor
- Remove pos at kitchen interior doorway
- Find new keystone for fireplace mantle.
- See image
- Re-point exterior
We will have Existing Conditions come through for a measure up in the next couple of weeks. Once that is done we can put together a sketch of what we are proposing i.e. porch deck master bath etc. so we can go to the city.